Question
Sonal completed 30% of work alone and left the remaining
work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find the time taken by Sonal and Vinod together to complete the whole work.Solution
Total time taken by Vinod alone to complete the work = (28/7) x 10 = 40 days Total time taken by Sonal alone to complete the work = (12/3) x 10 = 40 days Let total work be 40 units. Hence, the Required time will be = 40/2 = 20 days
Select the most appropriate word for the given group of words.
A traveller who moves from one region or country to another
Select the most appropriate option to substitute the bold segment in the given sentence.
Our guests arrived ; they are sitting in the garden.
The mandate of higher education is to nurture critical thinking that entail questioning; that includes a multiplicity of thoughts; and, most impo...
Select the most appropriate word segment for the bold word in the given sentence.
Pintu has been advised to reduce smoking by his family doctor...
Relentless
Select the most appropriate option to substitute the underlined segment in the given sentence. If there is no need to substitute it, select ‘No substi...
Select the option to complete the sentence most logically and appropriately.
He didn't see the whole film because
Select the most appropriate meaning of the given idiom.
A hard nut to crack
The finance ministry has consistently maintained that such information was confidential and …………..only be used to levy punitive taxes,if the cha...
Select the most appropriate option to improve the bold segment in the given sentence. If there is no need to improvement it,select, no improvement.
...