Question
A and B can do a work in 24 days and 32 days,
respectively. If A works on it for βxβ days and B works on it for βx β 1β days, then one-third of the work gets completed. Find the value of βxβ.Solution
Let the total work = 96 units {LCM of 24 and 32} Efficiency of A = 96/24 = 4 units/day Efficiency of B = 96/32 = 3 units/day According to the question; 4 Γ (x) + 3 Γ (x β 1) = (1/3) Γ 96 Or, 4x + 3x β 3 = 32 Or, 7x = 35 Or, x = 35/7 = 5
Which of the following dance is performed by Jasnath sect followers?
The device used for producing electric current is called
Freedom fighter Sagarmal Gopa was native of-
Which of the following is/are correct with reference to Moovalur Ramamirtham Ammaiyar (Ninaivu) Memorial Marriage Assistance Scheme?
I. The Sc...
The first English newspaper in India βBengal Gazetteβ was started by _______.
Which Prime Minister of India never presented the Union Budget?
What is the literacy rate of Lakshadweep as per the 2011 Census?
The following statements relate to the election of Indian President. Find out the wrong statement.
What is the nitrogenous waste excreted by shark?
Select the misspelled word.Β