Question

‘A’ and ‘B’ can complete a certain work in 18 days and 20 days, respectively. They started working together and worked till completion of the work for which they got Rs. 19000 as wage. Find the share of ‘B’ out of total wage.

A Rs 9500
B Rs 9200
C Rs 9000
D Rs 9400