Question
114 unit of work can be completed by P alone in 19 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (114/19) = 6 units/day According to question: 6 Γ 10 + (6 + x) Γ 6 = 114 Or, 60 + 36 + 6x = 114 Or, 6x = 114 β 96 Or, 6x = 18 Or, x = 3 Number of days taken by Q to complete the work alone = (114/3) = 38 days
Which state in India has the lowest birth rate?
What recognition did UNESCO recently award to West Bengal?
First Mineral Policy of Uttar Pradesh was declared on ........?
'Edge of Time' is the biography of which personality?
Where was the 25T Bollard Pull Tug, Bajrang, launched? Β
With which sport is the Murugappa Gold Cup associated?
Which of the following is the oldest university in the Uttar Pradesh?
Absolute alcohol is prepared from rectified spirit by using the following process:
Who among the following is known as the father of Indian nationalism?
‘Marsh Gas’ is