Question
P can do a piece of work in 10 days, Q can complete double the work in 30 days and R can do the work in 20 days. If all of them together earn Rs. 3900, then find the money received by Q.
More Time and work Questions
- A man completes a work in 16 days. A woman finishes half of that work in 10 days. How many days will they take together to finish 75% of the work?
- A and B can complete a task together in 26 days, while B alone takes 52 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- If Pawan takes twice the time that Qureshi takes or three times the time that Raju takes to finish a task, and all three working together can complete it i...
- 'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' alo...
- X can do a piece of work in 30 days. He worked at it for 5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?
- A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, then ...
- Rohan can do a piece of work in 30 days. Rohan with the help of Karan does the same piece of work in 20 days. If they are paid Rs 3696 for the work, then w...
- A can complete a work in 20 days, B in 30 days and C in 60 days. They work together for 5 days, then C leaves. In how many more days will A and B finish th...
- Sita is 50% more efficient than Simran. Working together, they finish the work in 24 days. How long will Sita take to complete the work alone?
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt