Question
A and B together can do a work in 8 days. If A can alone
do the same work in 12 days, then in how many days B alone will do the same work?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (8, 12) = 24 unit 1 day’s work of (A+B) = 24/8 = 3 unit 1 day’s work of A = 24/12 = 2 unit 1 day’s work of B = 3 - 2 = 1 unit Now, Time taken by B to completed the work = 24/1 = 24 days
Economic survey for a year is released on?
A four year mentorship programme ‘Project Arohan’ to provide guidance to students which state government has launched it recently?
How much more muscle mass did the gene-edited lamb show compared to normal sheep?
Consider the following statements about UNESCO's Prix Versailles award:Â
1.     Recently, IGI Airport has won this award.Â
2.  �...
What position has Ajay Singh assumed in the International Boxing Association (IBA)?
Which of the following is NOT included in the PM-Vidyalaxmi scheme's eligibility criteria for students?
What is the primary objective of the Public-Private Partnership (PPP) Beginner’s e-Course launched by the World Bank in collaboration with the Departm...
In November 2021, Oravel Stays Limited (OYO) appointed ___________ as strategic group advisor.
Where is the headquarters of the International Table Tennis Federation (ITTF)?
Who presided over the Monsoon Session 2023 of Rajya Sabha ?