Question

A can complete a work in 12 days and B can complete it in 18 days. They work together for 4 days, and the remaining work is completed by C alone in the next 6 days. In how many days can C complete the whole work alone?

A 10 days
B 12 days
C 13.5 days
D 15 days
E None of these