Question

'A' and 'B' together can complete 60% of a work in 36 days while 'B' and 'C' together can complete 75% of the same work in 40 days. If 'A', 'B' and 'C' worked on it for 20 days, 40 days and 40 days, respectively and completed the whole work, then find time taken by 'A' alone to complete the whole work.

A 180 days
B 120 days
C 240 days
D 360 days
E None of these