Question
'A' and 'B' together can complete 60% of a work in 36 days while 'B' and 'C' together can complete 75% of the same work in 40 days. If 'A', 'B' and 'C' worked on it for 20 days, 40 days and 40 days, respectively and completed the whole work, then find time taken by 'A' alone to complete the whole work.
More Time and work Questions
- 8 men can finish a work in 15 days. In how many days can 12 men finish the same work? (Same efficiency)
- X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before comp...
- The time taken by ‘A’ to build a wall alone is 45% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- Karan, Arjun and Krunal alone can complete a work in 35, 70 and 60 days respectively. All of them started working together but after 3 days from start Kara...
- Amit and Anaya can complete a task together in 20 days. If Anaya is 150% more efficient than Amit, how many days will Anaya alone take to finish the task?
- 'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining work ...
- A, B and C are hired at Rs 1050 to do a piece of work. A and B together complete 19/23 part of the work. And B and C together complete 8/23 of the work. Th...
- 12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?
- 4 girls working together for 1 day complete the same amount of work as 6 men working together for 1 day. The efficiency of 1 man is 50% of the efficiency o...
- A can complete a work in 12 days, and B can complete the same work in 18 days. How many days will they take to complete the work if they work together?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)