      β€˜A’ takes 6 days less than β€˜B’ to complete a work. β€˜B’ can complete 1/5th of the work in 6 days. Both of them started the work together and worked for 8 days. What fraction of work is left?

      A 1/5 Correct Answer Incorrect Answer
      B 2/15 Correct Answer Incorrect Answer
      C 4/15 Correct Answer Incorrect Answer
      D 2/5 Correct Answer Incorrect Answer

      Solution

      Time taken by β€˜B’ to complete the work = 6 Γ— 5 = 30 days

      Therefore, time taken by β€˜A’ to complete the work = 30 – 6 = 24 days

      Let the total work = 120 units

      Efficiency of β€˜A’ = 120/24 = 5 units/day

      Efficiency of β€˜B’ = 120/30 = 4 units/day

      Amount of work completed by them in 8 days = 8 Γ— (5 + 4) = 72 units

      Therefore, fraction of work left = 1 – (72/120) = 2/5