      Question

      Ravi, Mohit and Sohan can complete a work in 24 days, 48

      days and x days respectively. They started the work together and after 4 days, Ravi left the work. If Mohit and Sohan together complete the remaining work in 4 days, then find the value of x.
      A 14 Correct Answer Incorrect Answer
      B 12 Correct Answer Incorrect Answer
      C 19 Correct Answer Incorrect Answer
      D 23 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Work done by Ravi, Mohit and Sohan in 1 day = 1/24 + 1/48 + 1/x Work done by Mohit and Sohan in 1 day = 1/48 + 1/x According to the question, (1/24 + 1/48 + 1/x) * 4 + (1/48 + 1/x) * 4 = 1 Dividing both sides by 4, 1/24 + 1/48 + 1/x + 1/48 + 1/x = 1/4 1/24 + 2/48 + 2/x = 1/4 1/24 + 1/24 + 2/x = 1/4 1/12 + 2/x = 1/4 2/x = 1/4 - 1/12 2/x = 2/12 2/x = 1/6 x = 12