Question

    P, Q, and R can do a project individually in 10, 25, and

    20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days will Q and R need to finish the project?
    A 12 days Correct Answer Incorrect Answer
    B 8 days Correct Answer Incorrect Answer
    C 24 days Correct Answer Incorrect Answer
    D 18 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Total work = LCM of (10, 25, 20) = 100 units P’s efficiency = 100 ÷ 10 = 10 units/day Q’s efficiency = 100 ÷ 25 = 4 units/day R’s efficiency = 100 ÷ 20 = 5 units/day First 2 days: (10 + 4) × 2 = 28 units done Remaining = 100 - 28 = 72 units Q and R = (4 + 5) = 9 units/day Let x = number of days needed So, 9x = 72 → x = 8 Therefore, Q and R together will need 8 days to finish the rest.

    Practice Next
    ask-question