๐Ÿ“ข Too many exams? Donโ€™t know which one suits you best? Book Your Free Expert ๐Ÿ‘‰ call Now!


    Question

    P, Q, and R can do a project individually in 10, 25, and

    20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days will Q and R need to finish the project?
    A 12 days Correct Answer Incorrect Answer
    B 8 days Correct Answer Incorrect Answer
    C 24 days Correct Answer Incorrect Answer
    D 18 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Total work = LCM of (10, 25, 20) = 100 units Pโ€™s efficiency = 100 รท 10 = 10 units/day Qโ€™s efficiency = 100 รท 25 = 4 units/day Rโ€™s efficiency = 100 รท 20 = 5 units/day First 2 days: (10 + 4) ร— 2 = 28 units done Remaining = 100 - 28 = 72 units Q and R = (4 + 5) = 9 units/day Let x = number of days needed So, 9x = 72 โ†’ x = 8 Therefore, Q and R together will need 8 days to finish the rest.

    Practice Next
    More Time and work Questions
    ask-question