Question
A can complete a work in 18 days and B in 24 days. They
work on alternate days starting with A. In how many days will the work be completed?Solution
ATQ, Work in 2 days = (1/18 + 1/24) = 7/72 Remaining work calculation → 20 days
What is the enhanced scope for mandatory onboarding in Trade Receivables Discounting System (TReDS) for buyers as per the Budget 2025-26?
The Securities and Exchange Board of India (Sebi) has mandated the registration of index providers managing "significant indices" based on securities li...
A charge created over an asset as security that gives equal rights to all lenders is called _____Â
Which of the following statements about the Pradhan Mantri Fasal Bima Yojana (PMFBY) is/are correct?
1) It is a crop insurance scheme launched by...
Which of the following committees recommended the introduction of the Banking Regulation (Amendment) Bill, 2020 in the Indian Parliament?
When an existing company issues fresh shares, the existing shareholders get the priority to subscribe to these additional new shares, such shares are ca...
A manufacturing company experiences frequent fluctuations in production volume due to seasonal demand. Management wants a budgeting system that revises ...
Which of the following would have the primary responsibility of understanding the risks run by the bank and ensuring that the risks are appropriately ma...
Which of the following is NOT a Core Industry of India?
What are the criteria used to evaluate global financial centers?