Question
A can complete a work in 18 days and B in 24 days. They work on alternate days starting with
A can complete a work in 18 days and B in 24 days. They work on alternate days starting with
A. In how many days will the work be completed?
More Time and work Questions
- Ashish and Anil can do a piece of work in 20 days and 28 days respectively. Ashish completed 75% of the work. Find the time taken by Anil to complete the r...
- 35 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- A pipe can fill a tank in 20 hours, and B pipe can drain a tank in 15 hours. If a system of N pipes (fill pipes and drain pipes put together) can fill the ...
- P alone can finish a piece of work ‘M’ in 12 days while Q takes 8 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 10 ...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- ‘A’ alone can complete a work in 20 hours. ‘A’ started the work alone and left after working on it for 15 hours. If ‘B’ completed the rest of the work in 2...
- Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of ...
- Vijay can do a piece of work in 34 days and Sanjay can do the same work in 51 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work will...
- Karan is five times as efficient as Varun and twice as efficient as Arjun. If Varun takes 30 days to finish some work, then find the time taken by Karan an...
- ‘P’ takes 25 days to complete a piece of work. ‘Q’ is 25% more efficient than ‘P’. Find the time taken by them to complete 90% of the work together.
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt