Question
15 men can finish a work in 16 days by working 6 hours
a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?Solution
Let the efficiency of a man be 'x' units/day. Let number of extra men needed to finish the work be 'y'. ATQ; Total work = (15 + y) × x × 10 × 8 = 15 × x × 16 × 6 Or, 15 + y = 18 So, y = 18 − 15 = 3 Therefore, the number of extra men required = y = 3
Which one of the following diagrams best depicts the relationship among Cement, Bricks and Building materials?
The following Venn diagram shows the number of students who like to eat three different fruits (Dates, Mango, Cherry)
Which of the following diagram correctly represents the relationship between Tiger , Giraffe and Animals ?
If ‘+’ means ‘×’, ‘ – ‘ means ‘÷ ‘, ‘×’ means ‘ – &lsqu...
In the given figure, how many black are big but not pencil?

Choose the Venn diagram from the given options which represents the correct relationship amongst the following classes:
Crocodiles, Lizards, Rept...
Which of the following diagrams best depicts the relationship between Apple, Banana, Vegetable.
How many people likes ice cream?
The diagram represents the number of students studying different subjects. What is the number of students who study both Hindi and Chemistry?