Question
15 men can finish a work in 16 days by working 6 hours a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?
Solution
Let the efficiency of a man be 'x' units/day. Let number of extra men needed to finish the work be 'y'. ATQ; Total work = (15 + y) × x × 10 × 8 = 15 × x × 16 × 6 Or, 15 + y = 18 So, y = 18 − 15 = 3 Therefore, the number of extra men required = y = 3
More Time and work Questions
- 28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more women...
- Ravi and Sanjay take 54 days to build a fence. When they work along with Rahul, the work gets done in 36 days. Find the time Rahul alone would take to buil...
- ‘Elvish’ and ‘Farhan’ alone can finish a work in 25 and 50 days, respectively, while ‘Gaurav’ can complete 20% of the job in 10 days. All three start toget...
- 'A' and 'B' alone can complete a work in 10 days and 15 days, respectively. If they worked together and total wage received by them to complete the work is...
- 15 men working 9 hours daily can finish a task in 36 days, while 18 women working 6 hours a day complete the same task in 72 days. How many days will 6 men...
- Puneet and Qureshi together can complete (7/8)th of a piece of work in 9 days, Qureshi and Rohit together can complete (3/5)th of the work in 8 days and Pu...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- 'Rahul', 'Amit', and 'Vikram' together can complete a work in 20 days. 'Rahul' and 'Amit' together can complete the same work in 60 days. 'Vikram' alone ca...
- A can copy 80 pages in 20 hours, A and B together can copy 135 pages in 27 hours. Then Y can copy 20 pages in
- Deepak and Divya, alone can complete a work in 18 days and 27 days, respectively. They started the work together and left after 9 days such that the remain...