Question
Pooja can complete a task in 45 days and Kavita in 30
days. A third person, Mehul, is 20% more efficient than both of them combined. How many days will Mehul take to finish the work alone?Solution
Let total amount of work = 90 units (LCM of 45 and 30) Work done by Pooja in one day = 90/45 = 2 units Work done by Kavita in one day = 90/30 = 3 units Work done by Mehul in one day = 1.20 × (2 + 3) = 6 units Required time = 90/6 = 15 units
Which branch of the Indian armed forces has entered into a memorandum with the Indian Oil Corporation Limited to explore hydrogen and fuel cell technolo...
Which country's controversial Sado gold mine was recently registered as a cultural heritage site by UNESCO?
Where is the 10th edition of the India-Sri Lanka Joint Military Exercise MITRA SHAKTI 2024 being conducted?
With reference to the Sanchar Mitra Scheme, consider the following statements:
1. The scheme, launched by the Department of Telecommunications (D...
Consider the following statements regarding the DPIIT–GEAPP collaboration to promote climate-tech entrepreneurship in India:
1. The partnership...
Fill in the blanks with the correct options regarding recent decisions of the Employees’ State Insurance Corporation (ESIC):
1. The one-time am...
Who has assumed the presidency of the Financial Action Task Force (FATF) for the term 2024-2026?
Regarding the Uttarakhand government's "Pirul Lao-Paise Pao" campaign, consider the following statements:
A) The campaign aims to mitigate fore...
What unique feature does the PNB ANTAH DRISHTI Braille Debit Card offer to visually impaired customers?
Which two countries are considered the main engines for global growth, accounting for almost half of it?