Question
Time taken by 'X' and 'Y' to complete a work alone is 72
days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of the work.Solution
ATQ,
Let the total work be 360 units (LCM of 72 and 120) Efficiency of 'X' = (360 / 72) = 5 units/day Efficiency of 'Y' = (360 / 120) = 3 units/day Work to be completed = 25% of 360 = 90 units So, required time = (90 / (5 + 3)) = 90 / 8 = 11.25 days
- Which article of the Indian Constitution allows for the imposition of President's Rule in states?
- When was the Reserve Bank of India nationalized?
Which of the following defines disguised unemployment?
Consider the following statements regarding Atal Incubation Centre (AIC):
I. It is an initiative of the Atal Innovation Mission (AIM), NITI Aayog...
Which country hosted the 28th Conference of Parties (COP 28) to the United Nations Framework Convention on Climate Change (UNFCCC) in 2023? ( May 2023)
- In which year was the Election Commission of India officially established?
SmartFin, an end-to-end digital supply chain finance (SCF) platform, powered by Veefin Solutions has been launched that will help drive the required o...
 Recently Sirbaz Khan climbed Mount Everest without supplemental oxygen. Which country is he from?
Under the PM-KISAN scheme, how much annual financial assistance is provided to eligible farmers?
Where is the National Maritime Heritage Complex being developed in India?