Time taken by 'X' and 'Y' to complete a work alone is 72
days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of the work.Solution
ATQ,
Let the total work be 360 units (LCM of 72 and 120) Efficiency of 'X' = (360 / 72) = 5 units/day Efficiency of 'Y' = (360 / 120) = 3 units/day Work to be completed = 25% of 360 = 90 units So, required time = (90 / (5 + 3)) = 90 / 8 = 11.25 days
Whose family consists of total three members?
Which of the following can be coded as ‘sip zdp’?
If Reena exchanges position with Manish; and the one who teaches Maths exchanges position with Shabnam, who will be sitting at the extreme ends of row 1?
Height-wise, who among the following lies between Sohan and Rahul?
Which of the following combination is false?
Who among the following is designated as CGM?
How is S related to Q?
Priya is older than her cousin Manvi, Manvi's brother Bhaskar is older than Priya. When Manvi and Bhaskar are visiting Priya, all three like to play a g...
Six persons N, O, P, Q, R and S live in a six storey building but not necessarily in the same order. The bottommost floor is numbered as 1st and the top...
Which of the following statements is/are true?