'Karan', 'Ravi', and 'Deepak' together can complete a work
in 24 days. 'Karan' and 'Ravi' together can complete the same work in 96 days. 'Deepak' alone can finish the same work in how many days?Solution
ATQ,
Let the total work = 96 units (LCM of 24 and 96)
Combined efficiency of 'Karan' and 'Ravi' = (96/96) = 1 unit/day
Combined efficiency of 'Karan', 'Ravi', and 'Deepak' = (96/24) = 4 units/day
Efficiency of 'Deepak' = 4 - 1 = 3 units/day
Time taken by 'Deepak' to complete the work alone = (96/3) = 32 days
In a situation, when a company borrows money to be paid back at a future date with interest, it is known _____.Â
Stand Up India Scheme provide financial aid for Working Capital needs through which organisation?
Consider the following statements about National Housing Bank (NHB):
       I.           It was set up by an Act of Parliamen...
All single payment transactions of Rs. ______ crore and above undertaken by entities (non-individuals) should include remitter and beneficiary LEI info...
YUVIKA Programme will impart basic knowledge on space technology, space science, and space applications, while preference will be given to rural areas. ...
Which of the following best describes the primary purpose of the ASBA process?
Consider the following statements regarding the Priority Sectors Lending:
1. Besides microfinance groups, individual farmers are also eligible to...
Hornbill Festival is celebrated in which State?
The 'Ration Aapke Gram' scheme was recently launched in _____________.
Consider the following about 'Prior Learning Scheme’:
I. It is a skill certification programme implemented by National Skill Development Corpor...