Question
'Karan', 'Ravi', and 'Deepak' together can complete a work
in 24 days. 'Karan' and 'Ravi' together can complete the same work in 96 days. 'Deepak' alone can finish the same work in how many days?Solution
ATQ,
Let the total work = 96 units (LCM of 24 and 96)
Combined efficiency of 'Karan' and 'Ravi' = (96/96) = 1 unit/day
Combined efficiency of 'Karan', 'Ravi', and 'Deepak' = (96/24) = 4 units/day
Efficiency of 'Deepak' = 4 - 1 = 3 units/day
Time taken by 'Deepak' to complete the work alone = (96/3) = 32 days
Red worms have a structure named ______ which helps them in grinding their food.
Which one is correct for Pradhan Mantri Kisan Maan Dhan Yojana (PM-KMY)
For which position has Rajat Kumar Jain received approval from the Reserve Bank of India (RBI), and for which organization?
Consider the following statements regarding Sugarcane Industry in India:
1. It is a Weightloose industry.
2. Maharashtra is the largest su...
Deendayal Antyodaya Yojana -National Rural Livelihoods Mission observes Rashtriya Poshan Maah in the month of
…………………………State Government has launched the trees outside forest in India programme in association with USAID.
...The tagline of e-NAM is
As per Climate Change Performance Index 2023 ( CCPI, 2023) India is the only G-20 country in the top 10 ranks. The first three ranks in the overall ...
Recently Union Minister Shri Piyush Goyal announced for the integration of ODOP initiative with Open Network for Digital Commerce (ONDC), what is the fu...
The ‘ Central Sugarcane Research Institute’ in India is situated at_____?