Question
Pooja can finish a task by herself in 12 days, while when working together, Manju and Pooja can complete the same task in 6 days. Manju starts the work alone but leaves after 4 days, after which Pooja completes the remaining work on her own. If the total payment for completing the work under this arrangement is Rs. 8,400, how much of this amount does Manju receive?
More Time and work Questions
- A is twice as efficient as B. A and B together can complete a piece of work in 12 days. If B and C together can complete the same work in 18 days, then fin...
- Ravi can finish 50% of a job in 20 days, while Ramesh can finish 40% of the same job in 32 days. Both start working together, but Ravi leaves after some ti...
- Individual ‘M’ can do a piece of work in 40 days, while ‘M’ and ‘N’ together can do it in 16 days. If ‘N’ worked alone for 10 days and left, how many days ...
- ‘A’ and ‘B’ can complete a certain work in 20 days and 10 days, respectively. They started working together and worked till completion of the work for whic...
- ‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 10 days. If ‘B’ takes 5 days to complete the work a...
- A and B can do a job in 20 days and 30 days, respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete th...
- A alone can complete 70% of a work in 21 days while B takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then ...
- A can finish a job in 20 days while B can finish same job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have man...
- A can complete a work in 18 days and B in 24 days. They work on alternate days starting with A. In how many days will the work be completed?
- ‘D’ alone can complete a task in 20 days. ‘E’ is 40% less efficient than ‘D’. They worked together for 5 days, after which ‘D’ stopped working. What percen...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)