138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining work in 8 days. Find the number of days taken by Q to complete the whole work alone.

A 37.5 days Correct Answer Incorrect Answer
B 46 days Correct Answer Incorrect Answer
C 13.5 days Correct Answer Incorrect Answer
D 14 days Correct Answer Incorrect Answer
E 12 days Correct Answer Incorrect Answer

Solution

Let the efficiency of Q = x units/day Efficiency of P = (138/23) = 6 units/day According to question: 6 × 11 + (6 + x) × 8 = 138 Or, 66 + 48 + 8x = 138 Or, 8x = 138 – 114 Or, 8x = 24 Or, x = 3 Number of days taken by Q to complete the work alone = (138/3) = 46 days