138 unit of work can be completed by P alone in 23 days.
P started working alone and joined by Q after 11 days such that they completed the remaining work in 8 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (138/23) = 6 units/day According to question: 6 Γ 11 + (6 + x) Γ 8 = 138 Or, 66 + 48 + 8x = 138 Or, 8x = 138 β 114 Or, 8x = 24 Or, x = 3 Number of days taken by Q to complete the work alone = (138/3) = 46 days
The study of soil constitutes an independent branch of science known as:
Fertilizers, Pesticides, etc., are examples of
Kew, Queen or Mauritius are varieties of
Which tillage system involves leaving the soil undisturbed from harvest to planting, except for nutrient injection?
Which principle in experimental design involves grouping similar experimental units into blocks?
Which soil structure promotes optimal root growth and drainage?
Reforms aimed at improving institutional structures like tenancy laws and land ownership patterns to boost agricultural productivity are broadly known as:
What will be the cropping intensity of maize + urdbean - wheat rotation on 2 ha area?Β
_______ is the most widely used chemical for promoting seed germination.
_______is a band within the radial cell walls of endodermis that contain lignin.