πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      Worker 'A' can complete the entire task in 35 hours, and

      Worker 'B' can complete it in 40 hours, when working individually. If both 'A' and 'B' work together, how much time will it take for them to finish 60% of the task?
      A 13.2 hours Correct Answer Incorrect Answer
      B 11.2 hours Correct Answer Incorrect Answer
      C 9.6 hours Correct Answer Incorrect Answer
      D 16 hours Correct Answer Incorrect Answer

      Solution

      Let the total work = L.C.M of 35 and 40 = 280 units Then, efficiency of 'A' = 280 Γ· 35 = 8 units/hour Efficiency of 'B' = 280 Γ· 40 = 7 units/hour 60% of the work = 280 X 0.6 = 168 units Time taken by 'A' and 'B' working together to complete 60% of the work = 168 Γ· (7 + 8) = 11.2 hours

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question