Question
A contractor hired 80 workers to complete a work in 60
days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 80 extra workers are needed so that work gets completed on time.
More Time and work Questions
- Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___