Question
A contractor hired 80 workers to complete a work in 60
days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 80 extra workers are needed so that work gets completed on time.
In the question below, two sentences with one word in each highlighted in bold. From the options, choose the one that can replace the highlighted words...
Select the correctly spelt word.
Select the INCORRECTLY spelt word.
Directions: In each question below, word is used in four different ways. Choose the option in which the usage of the word is INCORRECT or INAPPROPRIATE....
Select the word which means the same as the group of words given.
Something that cannot be avoided
In each of the following questions, a word has been given and used in three statements. You are supposed to identify which of the statements/s use/s th...
Select the most appropriate synonym of the given word.
Diligent
Select the most appropriate synonym of the given word.
ACCURATE
Directions: In each of the following questions, a word has been used in sentences in THREE different ways. Choose the option corresponding to the sente...
- A word has been used in the sentences given below. Identify the statement(s) where the word has been used in a contextually and grammatically correct manne...