Question
A contractor hired 80 workers to complete a work in 60
days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 80 extra workers are needed so that work gets completed on time.
Which of the following terms will replace the question mark (?) in the given series?
IMHP, MPJQ, QSLR, UVNS, ?
If a mirror is placed on the line MN, then which of the answer figures is the mirror image of the given figure?
If STRICTURE is coded as TSUTCIRER, then how would INCULCATE be coded?
Question figure
There are two classrooms, A and B. If 20 students are shifted from A to B, the number of students in each room becomes the same. If 30 students are sent...
Statements:
All plants are vegetables.
Some plants are poisonous.
Conclusions:
I. All vegetables are poisonous.
I...
Select the Venn diagram that correctly represents the classes given below.
Wives, Lecturers, Working Mothers
Which of the following numbers will replace the question mark (?) in the given series?
213, 199, 235, 221, 257, 243, ?
Town M is to the west of Town D. Town C is to the south-west of Town D. Town D is to the north of Town B. Town A is to the south of Town C. Town M is to...
In a certain code language, ‘TIME’ is written as ‘3629’ and ‘BEND’ is written as ‘4582’.
How is ‘E’ written in that code lang...