Question
A contractor hired 80 workers to complete a work in 60
days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 80 extra workers are needed so that work gets completed on time.
What does HTML stand for in web technology?
Which layer of the OSI model provides flow control, error checking, and reliability in data transmission?
In C programming, which header file is commonly used to work with DMA?
What is the data transmission direction in a Token Ring network?
Store data in single table
State true/false
Once the email is compromised, all other sites and services online associated with this email can be compromised.
Which of the following backup types provides the fastest backup and recovery performance but requires the most storage space?
What is the purpose of a semaphore in synchronization?
In which programming language is dynamic memory allocation commonly used?
What does the term "phishing" refer to in the context of cybersecurity?