Question
A contractor hired 80 workers to complete a work in 60
days. After 40 days, it was found that only half of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 40 days and let total work be 2W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 80 extra workers are needed so that work gets completed on time.
In which year the Kheda Satyagraha was started in India?
What is India’s first solar mission, launched in 2022?
Who became the Chief Minister of Gujarat in September 2024?
Who has been elected as the new Chief Minister of Chhattisgarh as of (2025)?
The 36th National Junior Athletics Championship was held in _______ from February 6 to February 10, 2021.
 Indian Fundamental Rights have been taken from which of the following countries?
The scientific name of Tomato is_____