Question

    10 masons can build a wall in 15 days by working 8 hours

    per day. How many masons are required to build the wall in 10 days by working 12 hours per day?
    A 10 Correct Answer Incorrect Answer
    B 23 Correct Answer Incorrect Answer
    C 25 Correct Answer Incorrect Answer
    D 28 Correct Answer Incorrect Answer

    Solution

    ATQ, Number of masons required = 10