Question
A is twice as efficient as B, and B is thrice as
efficient as C. If C alone can complete a work in 30 days, then in how many days can they together complete the work?Solution
According to the question- C completes a work in 30 days.  B is three times as efficient as C. 3 ×B = 30 B = 10 days A is twice as efficient as B → 2 × A = 10 A = 5 days Then (A+B+C) together will finish the work. 5         10       30            30 6         3         1 Time =30/10=3days.
The output of the circuit below is _______
Maximum Power transfer occurs when the_____
Fill in the correct option for 28 blank space.
What is the backbone of MIS?
The latency of a network isÂ
A circuit has five branches with four nodes including reference node , then the number of linearly independent mesh equation would be_______
Which of the following statement is TRUE related to Alpha Beta pruning algorithm?
What is the primary purpose of the UNION ALL operator in SQL?
In object-oriented programming, when defining an interface method, which of the following statements is true regarding method parameters?
What is the shortcut for 'Undo' in most software?