      Question

      A and B together can complete a piece of work in 12 days

      and B and C can complete the same work in 18 days. If A worked for 5 days and B worked for 7 days and remaining work is completed by C in 19 days, then in how many days can B alone complete the work?
      A 18 days Correct Answer Incorrect Answer
      B 36 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 20 days Correct Answer Incorrect Answer

      Solution