📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A and B can finish a piece of work in 20 days and 30

      days respectively. Both work on alternate days. In how many days will the work be completed when A starts the work?
      A 12 Days Correct Answer Incorrect Answer
      B 24 Days Correct Answer Incorrect Answer
      C 18 Days Correct Answer Incorrect Answer
      D 36 Days Correct Answer Incorrect Answer

      Solution

      Both work alternately on alternate days. A starts first. Thus, 5 units can be worked in 2 days, so time taken to work 60 units = 60/5 =12 Days.

      Practice Next
      ask-question