Question

'R' takes 20 days to complete a task, and 'A' takes 30 days to do the same task. To finish the job in just 6 days, what percentage increase in their respective efficiencies is required by 'R' and 'A'?

A 75%
B 25%
C 100%
D 95%
E 55%