We can say that Let the total work = 60 units (L.C.M of 20 & 30) Efficiency of 'R' = 60/20 = 3 units /day Efficiency of 'A' = 60/30 = 2 units/day Their combined efficiency = 2 + 3 = 5 units/day To complete the work in 6 days, there combined efficiency should be 60/6 = 10 units/day Required percentage increase = {(10 – 5) × 100}/5 = 100%