P’s 3 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 75% of the work?
Ratio of efficiency of P and Q = 5:3 Let the efficiency of P and Q be 5x and 3x units per day respectively. Total work = 8x × 30 = 240x units Required time = (0.75 × 240x)/3x = 60 days
The division of population into two or more layers, each of which is relatively homogeneous and between which there are differences in opportunities, re...
_____ are the non-nutritive substances usually added to basal feed in small quantity for the fortification in order to improve feed efficiency and produ...
Bray-1 test is used for
The soils are called saline soils which have:
____is the oriented growth or movement in response to a chemical stimulus.
Which of the following states has very little alluvial soil?
What is the plant population for long rice?
Which of the following is a symptom of Yellow Leaf disease in sugarcane?
Which of the following is the traditional regulatory tool, which so far have been the focus of Food Safety and Standards Authority of India activities?
Which innovative platform was officially launched by Member of NITI Aayog, Professor Ramesh Chand, to streamline and enhance data management in the agri...