Question
Anita started working and left after 3 days and aftere
that Binita started the rest work and finished it in another 5 days. Had Anita left the work after working for 4 days and then Binita started the rest work, it would have been finished in another 2 days. In how many days can each of them alone finish the whole work?Solution
ATQ, (Anita = A and Binita = B) Let Anita finish the work in 'x' days and B in 'y' days Then, (3/x) + (5/y) = 1 Let (1/x) = A, and (1/y) = B then equations can be followed as- 3A + 5B = 1.......(1) 4A + 2B = 1.......(1) Solving both equations we get B = (1/14) days (1/y) = (1/14) Now, 3A + 5B = 1 3A + (5/14) = 1 A = 9/(14 × 3)= (3/14)days therefore B = 14 days and A = (14/3)days
What should come in place of '?' in the given series?
2Â 21Â 97Â 401Â 1617 ?
Which of the following numbers will replace the question mark (?) in the given series?
Select the figure t he will come next in the following figure series.
Referring to a girl, a woman says, "She is the daughter of my son
Select the letter-cluster from among the given option that can replace the question mark (?) in the following series.
LOT, NRX, KNS, OSY, ?
...Select the figure from the options that can replace the question mark(?) and complete the given pattern.
In a certain code language, if ANNOY is written as ZMMLB, then how will the SOUND be written in the same code language?
X-Ray : Radiologist :: Skin : ?
Select the correct option from the following options which could create a full square (3 out of 5 images below):
K, R, I, H, G and F are six candidates who are selected for the programme of M.Ed of ‘XYZ’ university. Each has to join in different months of the s...