      Question

      Ratio of the work done by P, Q and R in one day is 5:3:7

      respectively. They all together can complete the work in 35 days. Q and R worked on it for 20 days. In how many days P will complete the remaining work.
      A 70 days Correct Answer Incorrect Answer
      B 65 days Correct Answer Incorrect Answer
      C 88 days Correct Answer Incorrect Answer
      D 78 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount work be = 35 x 15 = 525 units Amount of work done by Q and R in 20 days = 20 x 10 = 200 units Amount of work left = 525 – 200 = 325 Required time = 325/5 = 65 days