Question
Ashish and Anil can do a piece of work in 15 days and 25
days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 25) = 75 units Efficiency of Anil = 75/25 = 3 units/day Remaining work = 75 x 0.6 = 45 units Time taken by Anil to complete the remaining work = 45/3 = 15 days
Bharat Muni, in his Natya Shastra, categorises musical instruments into four different parts. What is the categorisation of musical instruments by Bhara...
Which team won the 2024 edition of the Santosh Trophy, securing a record-extending 33rd title by defeating Kerala in the final?
What is the theme of World Asthma Day 2025?Â
Which of the following age groups is considered as working population or working age in India?
"PM Programme for Restoration, Awareness, Nourishment and Amelioration of Mother Earth" (PM-PRANAM) scheme launched in 2023 aims ___________.
Third Battle of Panipat was held in which year?Â
Night blindness is a condition caused by a deficiency of which vitamin?Â
Vizhinjam Port collaborated with which IIT to develop an AI-powered Vessel Traffic Management System (VTMS)?
Which of the following is not an assumption of the Monetary Policy Committee of April 2022?
In May 2023, ________ in Madhya Pradesh became the first city in India to adopt the localisation of the United Nationsmandated sustainable development g...