Question
Ashish and Anil can do a piece of work in 15 days and 25
days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 25) = 75 units Efficiency of Anil = 75/25 = 3 units/day Remaining work = 75 x 0.6 = 45 units Time taken by Anil to complete the remaining work = 45/3 = 15 days
When three parallel lines are cut by two transversals and the intercepts made by the first transversal are in the ratio 3 : 4, then the intercepts made ...
A cost incurred in the past and that cannot be recovered in the future is called ________.
If two interior angles on the same side of a transversal intersecting two parallel lines are in the ratio 2 : 3, then the greater of the two angles is:
If the ratio of speeds of 'A' and 'B' is 5: 6 and 'B' allows 'A' a start of 70 metres in a 1.2 km race, who will win the race and by what distance?
To which theory of conservation is related the first law of thermodynamics ?
Which of the following options represents sub-atomic particles found in Thomson’s model of an atom?
Which of the following statements is/are correct about National Family Health Survey (NFHS)?
       I.           It is conduc...
The President of India can promulgate ordinances when the Parliament is not in session under which article?
The speed of a train is 90 km/hr and it takes 15 seconds to cross a man. Find the time taken by train to cross a platform if the ratio of the length of ...
Aruna has a younger sister whose age is 8 years less than that of Aruna. If Aruna’s sister’s age is 18 years, then Aruna’s age is: