      Question

      If 15 men working 10 hours a day can make 25 quilts in

      18 days, then in how many days 20 men working 12 hours per day will make 20 quilts?
      A 9 Correct Answer Incorrect Answer
      B 10.5 Correct Answer Incorrect Answer
      C 15 Correct Answer Incorrect Answer
      D 7 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the number of days be x. According to question, => (15 ×  10 ×  18)/25 = (x ×  20 ×  12)/20 => x = 9