Question
P and Q can complete a work in 38 days and 57 days,
respectively. P, Q and R together can complete the work in 19 days. If R get a total wage of Rs. 6270 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (38, 57 and 19) = 114 units Number of units of work done by P alone in one day = 114/38 = 3 units Number of units of work done by Q alone in one day = 114/57 = 2 units Number of units of work done by P, Q and R together in one day = 114/19 = 6 units Number of units of work done by R alone in one day = 6 β 3 β 2 = 1 unit So, time taken by R alone to complete the work = 114/1 = 114 days So, per day wage of R = 6270/114 = Rs. 55
Pβs 3 days work is equal to Qβs 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 75% of ...
P alone can finish a piece of work βMβ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work βNβ wh...
Mike and Jenny alone can complete a task in 24 days and 40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny...
A and B individually can complete the work in 20 days and 30 days respectively. If the time taken by C alone to complete the work is 1.25 times the time...
Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after 5 ...
5 Pandavas can do a work in 18 days, 4 Kauravas can do the same work in 30 days. Now, in how many total days the total work be finished if 1 Panadva and...
- 14 chefs can cook 21 meals in 7 hours. How much time will 10 chefs take to cook 30 meals?
X can do a piece of work in 36 days. He worked at it for 6 days and then Y finished it in 20 days. In how many days can X and Y together finish the work...
- 25 employees working 9 hours a day take 20 days to complete a project. How many employees working for 8 hours a day are needed to complete twice the given ...
Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it ...