πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A and B can complete a task together in 22 days, while B

      alone takes 44 days to finish it. A began working alone and left after β€˜x’ days, after which B completed the remaining work in 33 days. Determine the percentage of the total work completed by A.
      A 25% Correct Answer Incorrect Answer
      B 15% Correct Answer Incorrect Answer
      C 20% Correct Answer Incorrect Answer
      D 40% Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 44 units
      Efficiency of (A + B) = 44/22 = 2 units/day
      Efficiency of β€˜B’ = 44/44 = 1 unit/day
      Amount of work done by β€˜B’ = 33 Γ— 1 = 33 units
      Percentage of work done by β€˜A’ = {(44 – 33)/44} Γ— 100 = 25%

      Practice Next

      Relevant for Exams:

      ask-question