📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A and B can complete a task together in 22 days, while B

      alone takes 44 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 33 days. Determine the percentage of the total work completed by A.
      A 25% Correct Answer Incorrect Answer
      B 15% Correct Answer Incorrect Answer
      C 20% Correct Answer Incorrect Answer
      D 40% Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 44 units
      Efficiency of (A + B) = 44/22 = 2 units/day
      Efficiency of ‘B’ = 44/44 = 1 unit/day
      Amount of work done by ‘B’ = 33 × 1 = 33 units
      Percentage of work done by ‘A’ = {(44 – 33)/44} × 100 = 25%

      Practice Next
      More Time and work Questions
      ask-question