Question
A and B can complete a work together in 18 days. If A
alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 3x days, then find the value of x.Solution
Time taken by A to complete the work = (x × 4) = 4x days Time taken by B to complete the work = (3x × 4/3) = 4x days According to question, => (1/4x) + (1/4x) = 1/18 => (1 + 1)/4x = 1/18 => 4x = 36 => x = 9
Which of the following Statements about Multiplier Effect is/are True?
I- When the government spends a rupee, overall income rises by a multiple ...
Consider the following statements regarding Phase II of the Swachh Bharat Mission (Grameen) [SBM (G)]
1) The program will be implemented...
What is the basic difference between Gross NPA and Net NPA?
I- Gross NPA is the total of Bank loans and Net NPA is the total of all kinds of loan...
Which of the following Statements about IREDA is/are True?
I- It is registered as Non-Banking Financial Company (NFBC) with Reserve Bank of India...
When Government expenditure is more than income, through which of the following ways, it does the deficit financing?
(1) From Banks
(2) Fr...
Which of the following statements about Prompt Corrective Action is/are True?
I- Prompt Corrective Action F...
Who among the following is not one of the eligible beneficiaries of PMUY?