Question

X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the value of X. 

A 34 Correct Answer Incorrect Answer
B 42 Correct Answer Incorrect Answer
C 55 Correct Answer Incorrect Answer
D 44 Correct Answer Incorrect Answer

Solution

According to question, => X × 45 = (X + 46) × 22 => 45X = 22X + 1012 => 23X = 1012 => X = 44