Question
A can do a work in 15 days and B in 18 days. If they work on it together for 5 days then in how many days the remaining work will be completed by B?
More Time and work Questions
- 12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
- 35% of the work done by Sunil in 8 days is equal to 70% of the work done by Raj in 3 days. If Sunil alone can do the work in 24 days, find the number of da...
- A can copy 80 pages in 20 hours, A and B together can copy 135 pages in 27 hours. Then Y can copy 20 pages in
- A and B together can complete a piece of work in 12 days. B and C together can complete it in 16 days. C and A together can complete it in 24 days. They al...
- P and Q can complete a work in 26 days and 39 days, respectively. P, Q and R together can complete the work in 13 days. If R get a total wage of Rs. 5850 t...
- 'Manoj' can complete some work alone in 40 days. 'Sohan' is twice as efficient as 'Rohan' and five times as efficient as 'Manoj'. If 'Manoj' and 'Rohan' st...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- A can complete a work in 10 days and B can complete the same work in 15 days. They work together for some days, then A leaves. B finishes the remaining wor...
- If 15 men or 10 boys can finish a task in 18 days, how long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approximate...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt