      Question

      A can do a work in 15 days and B in 18 days. If they

      work on it together for 5 days then in how many days the remaining work will be completed by B?
      A 9 days Correct Answer Incorrect Answer
      B 5 days Correct Answer Incorrect Answer
      C 7 days Correct Answer Incorrect Answer
      D 4 days Correct Answer Incorrect Answer

      Solution

      Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (15, 18) = 90 unit 1 day’s work of A = 90/15 = 6 unit 1 day’s work of B = 90/18 = 5 unit 1 day’s work of (A + B) = 6 + 5 = 11 unit Now, 5 day’s work of (A + B) together = 5 × 11 = 55 unit Remaining work = 90 – 55 = 35 Remaining work completed by B = 35/5 = 7 days