span >A and B together can complete a piece of work in 12 days while A alone can complete 70% of the work in 14 days. Find the time taken by B to complete 80% of the work.
More Time and work Questions
- Efficiencies of workers A, B, and C are in the ratio 5:7:8 respectively. If B and C can do the work in 9 days, then in how many days can A and B finish the...
- Mike and Jenny alone can complete a task in 24 days and 40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny's ...
- ‘A’ can do a piece of work in 20 days. ‘B’ can do 80% of the same work in 30 days. If they work together for the entire time and get paid Rs.1610, then fin...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- Numan does 4/ 5 half the work as Gagan in time. If together they take 16 days to complete a piece of work, then how long will Gagan take to complete the wo...
- Worker A can build a wall alone in 30 days. When A and B work together, they can complete the wall in 16 days. If B starts building the wall alone and work...
- Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the tot...
- X can do a piece of work in 20 days. He worked at it for 5 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
- A alone can do a piece work in 15 days and the time taken by A alone is 50% more than the time taken by B. They started work together alternatively startin...
- 15 men can do a piece of work in 10 days working 12 hours a day. How many men can do double the work in 25 days working 8 hours a day?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt