Question
A’ and ‘B’ together can complete a work in 10
days, while ‘B’ and ‘C’ together can complete the work in 20 days. If ‘B’ takes 8 days to complete the work alone then find the time taken by all three together to complete 57.5% of work.Solution
Let the total work = 40 units Efficiency of (A + B) = 40/10 = 4 units/day Efficiency of (B + C) = 40/20 = 2 units/day Efficiency of ‘B’ = 40/8 = 5 units/day Efficiency of (A + B + C) = (4 + 2 – 5) = 1 units/day Required time taken = (0.575 × 40)/1 = 23 days
What is the code for ‘ Love ’ in the given code language?
- If 'TABLE' is coded as '27', 'CHAIR' is coded as '22', then what is the code for 'LAPSE'?
If ‘SOLVED’ is coded as ‘XVQCJK’, ‘RACING’ is coded as ‘WHHPSN’, then, ‘WATCH’ is coded as ____ in the same code language.
...In a certain code language, ‘SAPLING’ is written as ‘VXSILKJ’. How will ‘MANIFEST’ be written in the same language?
In a certain code language, ‘SUPPLEMENTS’ is coded as ‘3’ and ‘MANUAL’ is coded as ‘3’ then ‘PRETTIER’ will be coded as ____ in the...
Which of the following is the code for “all are man” ?
In a certain code language, 'tim pac' means 'red colour', 'pit it tim' means 'red and black' and 'nac pit' means 'yellow black'. Which word in that lang...
What will be code for ‘Mobilize Lenders Authorities’ in the same code language?
In a certain code language, ‘GEMINI’ is coded as '63' and ‘TAURUS’ coded as '380'. What is the code of word ‘PISCES’ in the same coding lan...
What is the code of “Which Inclusive”?