Question
Aβ and βBβ together can complete a work in 10
days, while βBβ and βCβ together can complete the work in 20 days. If βBβ takes 8 days to complete the work alone then find the time taken by all three together to complete 57.5% of work.Solution
Let the total work = 40 units Efficiency of (A + B) = 40/10 = 4 units/day Efficiency of (B + C) = 40/20 = 2 units/day Efficiency of βBβ = 40/8 = 5 units/day Efficiency of (A + B + C) = (4 + 2 β 5) = 1 units/day Required time taken = (0.575 Γ 40)/1 = 23 days
______ company is all set to acquire Danske Bankβs IT centre in India?
Essarβs Power operational 400 kV inter-state transmission line in Madhya Pradesh to Chhattisgarh for Rs 1913 crore is being purchased by which group? ...
Recently the Union Home Minister Shri Amit Shah inaugurated the 120 feet tall polo statue in which of the following states of India?
Who was the first Indian woman to win an Olympic medal?
Who has issued the guidelines on the import of gold by Tariff Rate Quota (TRQ) holders under the India-UAE Comprehensive Economic Partnership Agreement ...
Where was the 3rd EPG meeting of BIMSTEC held recently?
Which of the following Ashram is situated in Sitapur district of Uttar Pradesh?
Which of these forts is known as Gateway of Haryana?
The important centres for cricket bats and other playing goods are
Who is new CEO of Unique Identification Authority of India (UIDAI) ?