Let the total work = 120 units Efficiency of horse who can complete the work in 40 hours = 120/40 = 3 units/hour Efficiency of horse who can complete the work in 60 hours = 120/60 = 2 units/hour Therefore, time taken by both horses to complete the work together = 120/(3 + 2) = 24 hours Therefore, time taken by the elephant to complete the work = 24 hours