Question
'A' and 'B' can finish a task together in 30 days. They worked together for 18 days and then left. The rest of the task was done by 'C' in 12 days. How many days will 'C' alone take to complete 75% of the total task?
More Time Questions
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- A and B can do a certain work in 6 hours, and A, B and C together take 4 hours to do the same. How long will it take for C alone to accomplish the task?
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- A thief steals a bike at 12:30p.m. and drives it at 48km/h. But the theft is discovered after half an hour. The bike owner starts to chase him on another b...
- A and B alone can complete a work in 30 and 60 days, respectively. 50% of the work is completed by C in 6x days, and the remaining work is completed by A a...
- Two cars start from a house at an interval of 10 minutes and travel at a speed of 20 km/hr. With how much speed (km/hr.) should a woman coming from the opp...
- A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone he can do th...
- A contractor assigned a job to three persons A, B and C. ‘A’ which is 25% less efficient than ‘B’ can complete 20% of a work in 8 days. ‘C’ takes 10 days m...
- 15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together t...
- A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)