Question
'A' and 'B' can finish a task together in 30 days. They worked together for 18 days and then left. The rest of the task was done by 'C' in 12 days. How many days will 'C' alone take to complete 75% of the total task?
More Time Questions
- Pipes A and B can fill an empty tank in 6 and 8 hours respectively, while pipe C can empty the full tank in 10 hours. If all three pipes are opened togethe...
- Four bells ring at 16, 24, 36, 42 minute intervals. If they ring together at 6.00 a.m., after how long would they next ring together?
- Question 3
- A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone w...
- Three bells ring at interval of 36 seconds, 40 seconds and 48 seconds respectively. They start ringing together at a particular time. They will ring togeth...
- If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?
- A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively. If B works daily and is supported by A and C on alternate days beginning wi...
- What % of a day is 30 minutes ?
- A thief steals a bike at 12:30p.m. and drives it at 48km/h. But the theft is discovered after half an hour. The bike owner starts to chase him on another b...
- A contractor hires 12 workers to complete a project in 20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)