'A' and 'B' can finish a task together in 30 days. They
worked together for 18 days and then left. The rest of the task was done by 'C' in 12 days. How many days will 'C' alone take to complete 75% of the total task?Solution
ATQ,
Fraction of work done by 'A' and 'B' = (18/30) = (3/5) Fraction of work done by 'C' = 1 - (3/5) = (2/5) So, number of days taken by 'C' to complete the entire work = 12 ÷ (2/5) = 30 days So, time taken by 'C' to complete 75% of the work = 30 × 0.75 = 22.5 days
Which sanctuary hosted the 8th Uttarakhand Bird Festival in 2024?
The Ministry of Statistics and Programme Implementation (MoSPI) recently launched an online platform providing real-time data to planners, policymakers,...
Which sport's international team competition is known as the Davis Cup?
Indian overnight index swap (OIS) rates showed a 10 month high due to offshore paying and triggering of stop losses, thus the swap rate hitting_______, ...
What is the primary purpose of the C-295MW transport aircraft received by the Indian Air Force from Airbus?
Who took on the role of Secretary General of BIMSTEC for the next three years, beginning in January 2024?
In which city did National Child Science Congress begin?
What is the primary focus of the 'Maiyan Samman Yojana' in Jharkhand?
Who from India won the UNEP Young Champions of the Earth 2025 award?
What percentage of ₹2000 banknotes in circulation as of May 19, 2023, has been returned by March 29, 2024?