Question
A and B can finish a work working on alternate days in
19 days, when A works on the 1st day. Similarly, they can finish the work working on alternate days in 19(5/9) days when B works on the first day. If C working alone can complete the work in 126 days, then in how many days can the work be completed by A, B and C together?Solution
Whether A starts or B starts, Work in 2 days by them will be same. So, work done in 18 days (9×2) will be also same in both cases. Now work done after 18 days will also be same, When A starts the work, after 18 days, A worked for last one day (19th day). When B starts the work, after 18 days, B worked for 19th day and A worked for 5/9th day in the end. So, A × 1 = B × 1 + A × (5/9) A – A × (5/9) = B 4A/9 = B A: B = 9: 4 So let A can do 9 units per day and B can do 4 units per day. So total work when A starts, => (A+B)’s alternate work in 18 days + A’s work in 19th day => (A+B)’s 2 days alternate work × 9 + 9 units => 13 units × 9 + 9 units = 126 units Now C can do this job in 126 days. So, C’s 1 day work = 126/126 = 1 units Hence A, B & C together can do this job in, => 126/(A+B+C) = 126/(9+4+1) = 126/14 = 9 days
15.99% of 549.99 ÷ 11.17 = ? ÷ 20.15
74.91% of 639.95 – 599.98% of 45 + 119.987 = ?
(4.88 × 5.76)2 - ?2 = 39.89 × 19.86
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exactvalue.)
(1800.23 ÷ 29.98) + (816.32 ÷ 23.9) + 1634.11 = ?
1449.98 ÷ 50.48 × 10.12 = ? × 2.16
36.05 × 5.02 + 12.052 = ? + 9.09 × 4.04Â
(31.9)3 + (34.021)² - (16.11)3 - (42.98)² = ?