Question
If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days how many men are required to dig additional 4 meter of the tunnel (of the same dimension) given that they work 4 hours a day for 4 day?
More Time Questions
- Question 1
- 15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together t...
- Two trains of length 200m and 160m respectively are running on parallel lines of rails. When running in the same direction the faster train passes the slow...
- An elephant can do a work as fast as two horses ‘A’ and ‘B’ can do it by working together. If horse ‘A’ alone can complete the work in 40 hours and horse ‘...
- Working alone, B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working toget...
- A thief steals a bike at 12:30p.m. and drives it at 48km/h. But the theft is discovered after half an hour. The bike owner starts to chase him on another b...
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- A and B can complete a work in 40 and 60 days respectively. They started a work which is to be completed in 20 days. But it was found that they are lagging...
- What is the angle traced by the hour hand in 23 minutes?
- Harish and Bimal can complete a task in 20 days. They worked at it for 15 days and then Bimal left. The remaining work was done by Harish alone, in 10 days...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)