Question
A, B and C can do a job working alone in 50, 75 and 20
days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?Solution
LCM of 50,75 an 20 is 300 units Each day A can do 300/50 =6 units  Each day B can do 300/75 =4 units Each day A can do 300/20 =15 units In each day 6+4+15=25 units for 4 days they do 4*25=100 units Each day A and B an together do 10 units Therefore 200/10 =20 days
What constitutes an unclaimed deposit according to the revised RBI guidelines?
CAAT stands for _________
The extent of cumulative cash flow mismatches could be arrived as under ______
Which of the following is a key feature of the SARFAESI Act?
What do Asset Reconstruction Companies do with financial assets?
India INX is an international stock exchange located in the IFSC, GIFT city. It is a subsidiary of _______
Which of the following is the key feature of the Security Receipts (SRs) issued by ARCs when acquiring stressed assets?
Consider the following statements regarding economic survey 2022-23:
1.   Financial Year (FY23) has a reversing trend of rural-urban infla...
What is the total dividend paid by LIC to the Government of India for the financial year 2023-24?
Which of the following statements is/are correct regarding Initial Public Offering (IPO) in India?
1)An IPO is a process by which a company raise...