Question
A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4th of the job working together?
More Time Questions
- A car is moving at a uniform speed of 35 km/h. What is the time it takes to cover 140 km?
- A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
- A and B can do a certain work in 6 hours, and A, B and C together take 4 hours to do the same. How long will it take for C alone to accomplish the task?
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- A can do (2/5) of a work in 6 days and B can do 30% of the same work in 3 days. They worked together for 4 days. The remaining work was completed by C alon...
- Girish can paint a picture in 4 days when he works for 8 hours per day. Due to illness, he could work for only 6 hours per day and was required to finish p...
- What is the angle traced by the hour hand in 23 minutes?
- A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 12 days, and C alone in 24 days, in what t...
- A and B can complete a work in 40 and 60 days respectively. They started a work which is to be completed in 20 days. But it was found that they are lagging...
- A trip from Mumbai to Pune takes 4 hours 30 minutes at a speed of 60 km/hr. How long (in hours) will it take to complete, if the speed is 15m/sec?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)