Question
A can do 50% of the job in 16 days, B can do 1/4th of
the job in 24 days. In how many days can they do 3/4th of the job working together?Solution
A can complete the whole work in 16*2=32 days B can complete the whole work in 24*4=96 days they both can complete the whole work in (96*32)/(128) =24 days The can complete (3/4)th work in 24*3/4 =18 days Â
Which village of the state was selected 1st prize for the water conservation category by the Union ministry of jal shakti?
Consider the following pairs;
Which of the above give...
By which year has the city of Dubai set goals to achieve Zero-Emissions public transportation?
What is the authorised capital of Sahakar Sarathi, the shared service entity for rural cooperative banks?
Consider the following statements:
1. Recently, researchers discovered a new species of jumping spider from Shendurney Wildlife Sanctuary
<...Consider the following statements about AUKUS Initiative:
1. It is a strategic partnership among Australia, the United Kingdom (UK), and the Un...
What was the year of establishment for the 'Fast Track Court' in Uttarakhand?
Consider the following statements regarding Sukanya Samriddhi Scheme:
1.           Under the scheme, parents or legal guardians can o...
Which district registered the maximum number of home stays for the financial year 2022-23 as of Dec 2022?
What is the theme of the Global Energy Leaders’ Summit (GELS) 2025?