📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Rakhi Special - Flat 52% off on All Courses from 6 to 10 Aug! âš¡ Enroll Now

    Question

    X, Y and Z together can complete a work in 15 days. X

    and Y together can complete the same work in 30 days. Z alone can finish the same work in how many days?
    A 45 days Correct Answer Incorrect Answer
    B 35 days Correct Answer Incorrect Answer
    C 30 days Correct Answer Incorrect Answer
    D 40 days Correct Answer Incorrect Answer

    Solution

    Let us assume Z alone can complete the work in 'x' days The efficiency of X, Y, and Z = (1/15) The efficiency of X and Y = (1/30) The efficiency of Z = (1/x) = (1/30) + (1/x) = (1/15) By solving the value of 'x' ⇒ x = 30 days ∴ The required result will be 30 days.

    Practice Next
    ask-question