Question
Three bells ring at interval of 36 seconds, 40 seconds and 48 seconds respectively. They start ringing together at a particular time. They will ring together after every
More Time Questions
- In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
- A contractor hires 12 workers to complete a project in 20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How...
- A and B can finish a work working on alternate days in 19 days, when A works on the 1st day. Similarly, they can finish the work working on alternate days ...
- What % of a day is 30 minutes ?
- 15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together t...
- A car running with a speed of 69 km/hr takes 28 hours to go from 'A' to 'B'. If on the way back from 'B' to 'A', the car takes 20% less time than it takes ...
- Question 7
- P and Q can complete a project in 15 days and 10 days, respectively. They started doing the work together, but after 2 days, Q had to leave and P alone com...
- Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
- A man is travelling at a speed of 100 km/h such that he will take 60 minutes to reach his destination. But after completing half the journey, the man took ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)