Question
A can complete a certain work in 30 days. B is 25% more
efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone will complete the remaining work in:Solution
A can complete the work in = 30 days Efficiency of A (A’s 1 day’s work) = 1/30 Efficiency of B (B’s 1 day’s work) = 1/30 × (125/100) = 1/24 Efficiency of B (B’s 1 day’s work) = 1/30 × (125/100) = 1/24 Efficiency of C (C’s 1 day’s work) = 1/24 × (120/100) = 1/20 Let the remaining work be complete by B in x days. According to the question, => 3(1/30 + 1/24 + 1/20) + x/24 = 1 ⇒ 3 [(4 + 5 + 6)/120] + x/24 = 1 ⇒ 15/40 + x/24 = 1 ⇒ x/24 = 1 – 3/8 ⇒ x/24 = (8 – 3)/8 ⇒ x/24 = 5/8 ⇒ x = 5/8 × 24 = 15 days
According to the Bloomberg Billionaires Index, who is the 3 rd Richest person in the world?
- The "Shatapatha Brahmana" is associated with which Veda?
- Which of the following accurately describes Article 85 of the Indian Constitution?
Match the schemes with their respective states:
Which of the following statements is/are incorrect?
1. The Maritime Decarbonization Conference was co-hosted by the Ministry of Ports, Shipping, ...
Which life insurance company has announced that the overseas branch of its international subsidiary will now offer US Dollar denominated life and health...
Which Indian financial regulator oversees the capital and commodities markets?
Which organization recently launched “Global Strategic Preparedness, Readiness and Response Plan (SPRP)”?
Which e-commerce platform has collaborated with the Directorate General of Foreign Trade to co-create capacity building sessions, training and workshops...
What is the theme for the 2025 Republic Day tableaux?