A contractor assigned a job to three persons A, B and C. ‘A’ which is 25% less efficient than ‘B’ can complete 20% of a work in 8 days. ‘C’ takes 10 days more than ‘B’ to complete the same work. ‘A’ and ‘B’ started working together and after 4 days C joined them. Due to some personal emergency ‘A’ left after 5 more days and rest of the work is completed by 'B' and 'C', together. Find the total time taken to complete the whole work.
Time taken by ‘A’ to complete the work alone = 8/0.2 = 40 days Time taken by ‘B’ to complete the work alone = 0.75 × 40 = 30 days Time taken by ‘C’ to complete the work alone = 30 + 10 = 40 days Let, the total work = 120 units Efficiency of ‘A’ = 120/40 = 3 units/day Efficiency of ‘B’ = 120/30 = 4 units/day Efficiency of ‘C’ = 120/40 = 3 units/day Work completed in 4 days = 4 × (3 + 4) = 28 units Work completed in next 5 days = 5 × (3 + 4 + 3) = 50 units Time taken by ‘B’ and ‘C’ to complete remaining work together = (120 – 78)/7 = 6 days Therefore, total time taken = 4 + 5 + 6 = 15 days
How many triangles are there in the figure?
Count the number of squares in the given figure.
In the adjoining figure, if the centres of all the circles are joined by horizontal and vertical lines, then find the number of squares that can be form...
Count the number of squares in the given figure.
Find the number of triangles in the given figure.
How many triangles is therein the following figure?
How many quadrilaterals are there in these given figures?
Find the number of quadrilateral in the given figure?
In the adjoining figure, if the centres of all the circles are joined by horizontal and vertical lines, then find the number of squares that can be form...
How many Quarilaterals are there in the following figure?