A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 12 days. If ‘B’ takes 20 days to complete the work alone then find the time taken by all three together to complete 47.5% of work.
Let the total work = 120 units Efficiency of (A + B) = 120/8 = 15 units/day Efficiency of (B + C) = 120/12 = 10 units/day Efficiency of ‘B’ = 120/20 = 6 units/day Efficiency of (A + B + C) = (15 + 10 – 6) = 19 units/day Required time taken = (0.475 × 120)/19 = 3 days
Which is the most widely accepted model to explain the formation and evaluation of the solar system?
In which of the following Stadiums does the Madhya Pradesh Cricket team play the majority of their home games in Ranji Trophy?
Which of the articles given are related to citizenship?
Kanishka, belonged to the:
Which Indian shooter won two Paralympic medals in the single edition of Paralympic on 3 September 2021?
Which of the following activities is NOT included in the functions of the Bank for International Settlements (BIS)?
What is not true about the Atal Pension Yojana Scheme , according to the given statements-?
i. One can get Rs 1,000 to Rs 5,00...
What is the present Statutory Liquidity ratio (SLR) of the RBI?
Match list I with list II and select the correct answer using the code given below the list
As per the provisions of the Maternity Benefit Act, 1961, the maximum period for which a female employee shall be entitled to leave with wages as mater...