A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 12 days. If ‘B’ takes 20 days to complete the work alone then find the time taken by all three together to complete 47.5% of work.
Let the total work = 120 units Efficiency of (A + B) = 120/8 = 15 units/day Efficiency of (B + C) = 120/12 = 10 units/day Efficiency of ‘B’ = 120/20 = 6 units/day Efficiency of (A + B + C) = (15 + 10 – 6) = 19 units/day Required time taken = (0.475 × 120)/19 = 3 days
What is the average of first 22 multiples of 2.2?
Who has secured the first position in the World of Statistics ranking of the most criminal countries recently?
A spent 10% of his monthly income on study and 50% of the remaining on rent. If amount spent on rent is Rs. 1350, then find the amount spent on study
Which of the following legislations is comprehensive social security legislation?
Which of the following pair is not correctly matched?
Which one of the following elements is not naturally found in human beings?
Consider the following statements regarding the evolution of budget in India:
1. System of budget was introduced during the tenure of Lord Cannin...
Which country among the following is the biggest producer of cotton?
A 60 m long train travels at a uniform speed of 72 km/hour. It passes non-stop along the 600 m platform of a wayside station. What is the elapsed me fo...
Consider the following statements:
1. Prime Meridian passes through Greenwich and is at 0° Longitude.
2. International Date Line, on...