Question
A and B together can complete a piece of work in 35 days
while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12.5% of the work.Solution
Time taken by A to complete the whole work = 20/0.50 = 40 days Let total work = 280 units Amount of work done by A and B together in one day = 280/35 = 8 units Amount of work done by A alone in one day = 280/40 = 7 units Amount of work done by B in one day = 8 – 7 = 1 units Desired time = 0.125 × 280/1 = 35 days
Where are the headquarters of the Reserve Bank of India?
Which of the following is NOT true about microfinance?
i. These loans are unsecured loans of Upto Rs. 1 lakh mostly given following group lending...
What is true about CGTSME?
KYC used in the Banks in India, the main aim for using KYC in bank is_____
The main purpose of preparing a Bank Reconciliation Statement is:
In RTGS, S stands for
SWIFT code consists of ________ digits.
_________ bank has partnered with MobiKwik for co-branded virtual Visa prepaid card.Β
Which of the following is the 8 digit code and extended upto 11 digits?
In which year the first Bank of India was established?