Question
A and B together can complete a piece of work in 35 days
while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12.5% of the work.Solution
Time taken by A to complete the whole work = 20/0.50 = 40 days Let total work = 280 units Amount of work done by A and B together in one day = 280/35 = 8 units Amount of work done by A alone in one day = 280/40 = 7 units Amount of work done by B in one day = 8 – 7 = 1 units Desired time = 0.125 × 280/1 = 35 days
Which Indian pistol, featuring a 17+1 round capacity, is the first to integrate a Red Dot Sight in India?
Which Indian port is now the only authorized entry point for importing jute from Bangladesh?
The PM-AASHA scheme has been implemented to support remunerative prices for farmers. Which of the following is NOT a component of the scheme's strategy ...
Former Chief Minister of undivided Andhra Pradesh Nadendla Bhaskara Rao passed away on 22 April 2026. How many days did he serve as Chief Minister?
Which geological site in Maharashtra has been added to UNESCOβs Tentative List in 2025?
Who is the first Asian and Indian to receive the Hans von Hentig Award for significant contributions to victimology?
The Mumbai Metropolitan Region Development Authority (MMRDA) recently signed an agreement with which company to provide financial support of over Rs 850...
What are the four strategic pillars of the Government of India - United Nations Sustainable Development Cooperation Framework 2023-2027?
Which two countries recorded investment growth of over 40% in Indian mutual funds in FY25?
- ZooWIN is a digital platform focused on real-time tracking of stocks for which vaccines?