Question
A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12.5% of the work.
More Time Questions
- A contractor hires 12 workers to complete a project in 20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. How...
- A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left....
- In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
- Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
- A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
- A and B can together complete a task in 18 hours. After 6 hours A leaves. B takes 36 hours to finish rest of the task. How many hours would A have taken to...
- Harish and Bimal can complete a task in 20 days. They worked at it for 15 days and then Bimal left. The remaining work was done by Harish alone, in 10 days...
- A mango kept in a basket doubles every one minute. If the basket gets completely filled by mangoes in 30 min then in how many minutes half of the basket wa...
- A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working t...
- Two trains of length 200m and 160m respectively are running on parallel lines of rails. When running in the same direction the faster train passes the slow...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt