Question
A is thrice as efficient as B and can finish a piece of
work in 28 days less than B. B can finish this work in how many days?Solution
Ratio of efficiency of A and B = 3: 1 A will take 1/3 of time as compared to B. Say, B takes 3x days and A takes x days. ∴ 3x – x = 28 ⇒ x = 14 ∴ B takes 14 × 3 = 42 days to do the work
Consider the following statements:
(i) Haiderpur Wetland of Western Uttar Pradesh (UP) has been recognized as 47th Ramsar site in the country and...
In the OBICUS survey, what does U stand for?
In economics, what does 'Budget Surplus' mean?
Which of the folloinwg statement is not correct about Urban Co-operative Banks (UCBs):
Of which of the following organisations is India NOT a member?
In 2023, Prime Minister Narendra Modi, on the occasion of which of the following day paid tributes to Chhatrapati Shivaji Maharaj, and unveiled a grand ...
CAPTCHA is a type of security measure known as challenge-response authentication. What does P stand for?
The first railway line in India was laid in the year 1853 from Bombay to _______.
In which year was The Reserve Bank of India was established?
Select the option that shows the correct match of an organisation and its headquarters.