Question
A is thrice as efficient as B and can finish a piece of
work in 28 days less than B. B can finish this work in how many days?Solution
Ratio of efficiency of A and B = 3: 1 A will take 1/3 of time as compared to B. Say, B takes 3x days and A takes x days. ∴ 3x – x = 28 ⇒ x = 14 ∴ B takes 14 × 3 = 42 days to do the work
Find the next number in the series: 8, 16, 32, 64?
United Nations Security Council extended the peace security mission in which of the following African countries?
Each sentence below has one or two blanks. Fill in these blanks with most appropriate word/ phrase from the four options that are given following each s...
What does the term "regatta" refer to?
Which of the following company has become the 12th company to attain the Maharatna status?
Radha Reddy and Raja Reddy are famously known for the ________ form of dance.
Which of the following is full form of NDRF?
________ of the Constitution of India provides that no discrimination can be made against a citizen on grounds only of race, religion, caste, or place o...
Head Quarter of “Bandhan Bank” is located in?
Which of the following statements is NOT correct regarding 'shramshakti"?